Inspection contents of basement water pump room

DATE:2025-01-16 VIEWS:186

1. Indoor lighting and hygiene

Testing method: Visual inspection.

Inspection requirements: Promptly repair damaged lighting fixtures and light sources, keep the ground clean and free of standing water, ensure that the drainage ditch cover is flat and complete, and that the walls are free of dust and spider webs.

Inspection cycle: every two weeks.

2. Water source

Testing method: Visual inspection.

Inspection requirements: Test the water supply capacity of the water source.

Inspection cycle: Annual.

3. Fire water pool

Testing method: Visual inspection.

Inspection requirements: The water level is normal, the float valve is intact and usable, and the alarm function of the water level alarm is normal; There is no leakage, the water level control system is normal, and it is required to be at full water level and below half of the water level.

Inspection cycle: monthly.

4. Pipeline system

Testing method: Visual inspection.

Inspection requirements: There should be no running, emitting, dripping, or leaking phenomena, and the insulation of the pipeline should be undamaged; Whether the valve switch is flexible and the one-way valve is normal; The switch position is clearly marked, the switch position is correct, the operating handle and handwheel are complete, without rust, the pressure gauge is normal, and the value meets the requirements of this project.

Inspection cycle: quarterly.

5. Filter

Detection method: Manual slag discharge.

Inspection requirements: No damage or blockage, in good condition.

Inspection cycle: quarterly.